Part 1: Widgetco is making a prototype of a new product. The product consists of two subassemblies. Before building either subassembly, the firm must purchase raw materials and train workers. Before the subassemblies can be combined, subassembly 2 must be inspected. The following table describes the project:
Activity | Description | Requires | Duration (Days) |
A | Train Workers | -- | 6 |
B | Purchase Materials | -- | 9 |
C | Make Subassembly 1 | A, B | 8 |
D | Make Subassembly 2 | A, B | 7 |
E | Inspect Subassembly 2 | D | 10 |
F | Combine Subassemblies | C, E | 12 |
G | Subassembly 2 Safety Report | E | 6 |
How quickly can Widgetco complete this project?
Part 2: Management imposes a deadline of 25 days to complete the project. Fortunately, each of activities may be shortened by up to 5 days at the following cost per day:
Activity | Cost to Shorten by One Day |
A | $10 |
B | $20 |
C | $3 |
D | $30 |
E | $40 |
F | $50 |
G | $15 |
What is the cheapest way for Widgetco to complete the project in 25 days?